New asphalt and stripes for Navajo Route 57
TSE BONITO, N.M. — On Oct. 2, the Navajo Division of Transportation (NDOT) completed an asphalt replacement project that addressed damaged pavement on Navajo Route 57 in Gad’iiahi/To’Koi Chapter.
The scope of work included erosion control, saw cutting and removing the existing asphalt, subgrade preparation, and shaping of the road.
Essential to the project was the placement of aggregate base course at an 8 inch thickness and hot asphalt concrete paving at a 3 inch thickness. Yellow striping completed the project.
Navajo-owned Arrow Indian Contractors out of Scottsdale, Arizona, were the selected contractor and Navajo DOT Project Manager Marlinda Littleman oversaw the $182,253 project, which was funded through New Mexico Capital Outlay funding.
“The pavement on this stretch of N57 was badly damaged and in dire need of replacement,” Littleman said. “A big thanks goes out to Navajo DOT civil engineer Max Bighorse who completed the plan and design for the project.”
Because the project was funded through New Mexico Capital Outlay, the plan and design had to be approved by the New Mexico Department of Transportation (NMDOT). Before construction could commence, NDOT had to obtain several certifications that were issued by NMDOT.
Navajo Nation President Jonathan Nez said he appreciates partnerships like these that help bring important projects to completion.
“Because our Nation spans four states, we often rely on partnerships to bring multi-jurisdictional projects to completion,” he said. “We also appreciate our Navajo contractors and engineers who are fundamental to making these projects happen.”
NDOT Executive Director Garret Silversmith said N57 connects area residents to U.S. Route 64 that leads eastward to Shiprock, New Mexico.
“It was important for Navajo DOT to fix this damaged section of N57,” Silversmith said. “The road provides access to many governmental services, public safety and health care services and other necessities like shopping and employment.”
Information provided by NDOT
- Hardship Assistance payments set to begin Jan. 18
- Hardship Assistance payments begin Jan. 18
- Navajo CARES Act funding to continue through 2021
- 25% of Navajo applicants at risk of not receiving Cares Act funds
- 11 miles of Navajo Route 27 paved between Chinle and Nazlini
- Governor proposes changes to gaming on and off reservation
- COVID-19 has taken much from Jerrel Singer, but the Native artist looks toward the future with hope
- Why ‘Come and Get Your Love’ now? After 46 years ‘the time has come’
- Trump administration releases vision for Native Americans
- With looming deadline, Nation works to fix Hardship Assistance Program application errors
- 25% of Navajo applicants at risk of not receiving Cares Act funds
- Hardship Assistance payments set to begin Jan. 18
- Navajo CARES Act funding to continue through 2021
- With looming deadline, Nation works to fix Hardship Assistance Program application errors
- Hardship Assistance payments begin Jan. 18
- More than 290,000 Navajo Nation members apply for Hardship Assistance Program
- Why ‘Come and Get Your Love’ now? After 46 years ‘the time has come’
- Trump administration releases vision for Native Americans
- Checkpoints erected on Hopi reservation, lockdown to continue through Feb. 1
- I-40 resort project near Navajo Nation stirs culture controversy
SUBMIT FEEDBACK
Click Below to: