U.S. 89 to open March

Paving began March 11, students from Bitter Springs and Marble Canyon areas likely the first to travel new roadway

Above and below: Arizona Department of Public Safety (ADOT) crews pave a 500-foot section of U.S. 89. Photo/ADOT

Above and below: Arizona Department of Public Safety (ADOT) crews pave a 500-foot section of U.S. 89. Photo/ADOT

FLAGSTAFF, Ariz. - Two years after a landslide ripped apart a 500-foot section of U.S. 89 and split the communities of Bitter Springs and Page, the Arizona Department of Transportation (ADOT) anticipates reopening the highway to traffic on the afternoon of March 27, barring any potential weather delays or mechanical breakdowns during the paving process, which began March 11.

Page Unified School District buses are expected to be the first vehicles to pass through the newly rebuilt roadway. Students from the Bitter Springs and Marble Canyon areas have been among the most affected by the U.S. 89 closure, which has remained in place following the Feb. 20, 2013, geologic event approximately two miles north of the U.S. 89/U.S. 89A junction near the community of Bitter Springs.

Following the paving of temporary U.S. 89 in August 2013, U.S. 89T has served as the detour route for drivers headed to and from the Page and Lake Powell areas, but residents and students in the Bitter Springs and Marble Canyon communities have still had to go out of their way to travel to and from Page and Lake Powell.

"The reopening of Highway 89 is great news for Page Unified School District and the families that we serve in the communities of Marble Canyon, Bitter Springs and Cedar Ridge," said Page Unified School District Superintendent Jim Walker. "The district will be now be able to re-establish our traditional bus runs to these communities, which will reduce the time that some of these children spend on our buses by up to an hour on a one-way trip. I would like thank our families for their efforts to continue to support their children's school attendance during this very challenging time."

Prior to the March 27 reopening, crews will complete the paving, install rumble strips and guardrail and add temporary striping and pavement markers along the roadway.

Prior to launching the $25 million repair project last summer, which included removing approximately one million cubic yards of rock material to realign the roadway and construct a downslope rock buttress at the base of the Echo Cliffs to stabilize the area, ADOT had to clear several hurdles to move the project forward.

The ultimate repair of US 89 is the final step in fulfilling ADOT's three-pronged approach to the U.S. 89 landslide incident, which included providing immediate emergency access, conducting a geotechnical investigation and restoring essential traffic to the area. Paving U.S. 89T (Navajo Route 20) has been the short-term solution for motorists driving to and from Page.

"ADOT recognizes the importance of this corridor and what it means to the communities of Bitter Springs, Cedar Ridge and Marble Canyon," said ADOT Intermodal Transportation Division Director Steve Boschen. "While the Feb. 20, 2013, landslide event was certainly unexpected and a severe blow to the area, it was a reminder about how critical transportation infrastructure is to the motorists, businesses, local residents and schoolchildren who rely on it every day."

After an extensive geotechnical assessment identified the necessary repairs in July 2013, ADOT retained an engineering firm and developed plans for the eventual repair; finalized all federally required environmental reviews that included cultural, biological and water quality measures; and completed plans for the required right-of-way easements.

Comments

Comments are not posted immediately. Submissions must adhere to our Use of Service Terms of Use agreement. Rambling or nonsensical comments may not be posted. Comment submissions may not exceed a 200 word limit, and in order for us to reasonably manage this feature we may limit excessive comment entries.